Demand Disruption¶
A large new load arrives: data centres as the example
What is in the model today¶
Candidate nodes for data centres. In grid models, every demand-carrying node is scored for how likely it is to attract data centres. The score uses PeeringDB, a public registry of interconnection facilities, as a spatial prior: each facility is snapped to its nearest demand node, and a node's score is the sum of the facilities' interconnection counts. The five highest-scoring nodes are pre-selected; the rest are listed so a user can swap them in. Where PeeringDB coverage is thin, the remaining slots are filled from the nodes with the largest demand share. The table is written to SubRES_Data_Centers_Trans.xlsx in each grid build.
Demand placed where it is. Existing demand is already on the grid by population and by industrial site (see Electricity Demand), so a new load lands on a network that already carries a realistic pattern.
Demand variants. The AR6 climate categories in the scenario file carry different demand growth (Germany 2050: 934 TWh in C4, 1,042 TWh in C1), which bracket the background growth a new load is added to.
What the user sets¶
- How much, and how fast. The national data-centre load, in GW by year, is a user input. The pipeline ranks places; it does not forecast the industry.
- Where. Accept the pre-selected nodes or swap in others from the ranked list (the
includecolumn). - How it runs. Hours of operation and any flexibility the load offers.
What it can show¶
- Which corridors and nodes come under strain.
- Whether the load is met by new local generation, by imports along existing corridors, or by keeping older plants running longer.
- The cost and emissions of the extra demand, against the reference.
- How the answer changes with location: the same gigawatts at a well-connected node and at a weak one.
Not built yet¶
- No national data-centre growth path is supplied by default.
- The PeeringDB score ranks nodes; it is not an inventory of existing data centres, and coverage varies by country.
- The scoring is in grid models only.