Grid Representation

From the real transmission network to a set of nodes and corridors a model can solve

Watch first: Germany's Power Grid (1:59, narrated). Generated from a real build of the German model; every number on screen traces to a file. The sections below follow the video in the same order, with the rules and file names behind each step. Also: interactive version · India · all method videos.

A VerveStacks model does not treat a country as one point. It keeps a reduced copy of the country's high-voltage network: a set of nodes, each a real substation, joined by corridors. Plants, demand, wind and solar are all attached to nodes, so the model sees where power is made, where it is used, and what lies between.

The page uses three terms throughout:

Term Meaning
Node A substation that survives simplification. In the code and file names it is a bus; in the model it is the electricity commodity e_<node>.
Corridor All the lines between two nodes, taken together. In the model it is the process g_<node>-<node>.
Cluster A group of wind or solar cells attached to one node (see Renewable Energy Characterization).

The method in five steps

  1. Start from the mapped network: every substation and line in OpenStreetMap.
  2. Choose which substations stay as nodes, by rule.
  3. Fold every other substation into its nearest node.
  4. Merge the lines between each pair of nodes into one corridor.
  5. Attach plants, demand, wind and solar to the nodes.

How many nodes to keep is a choice, not a property of the data. The same method gives Germany 37, 45, 481 or 795 nodes, and India 18, 50 or 348.

1. The starting network

Dataset Coverage Source
eur Europe OpenStreetMap, as prepared in the PyPSA-Eur prebuilt network
kan Worldwide OpenStreetMap, prepared the same way

Each dataset holds substations (with voltage and coordinates), AC lines (with voltage, length and a thermal rating) and DC links.

Country Dataset Substations Lines Voltages
Germany eur 795 1,029 220 and 380 kV
India kan 348 459 400 and 765 kV

Starting networks for the two example countries

Coverage outside Europe is thinner. India's mapped network is almost all 765 kV and has no cross-border lines.

2. Which substations stay

The simplifier (1_grids/kan_grid_simplifier/) keeps substations for four reasons. Every node records the reason it was kept in input_network/bus_mapping.csv.

Reason Rule Tag in bus_mapping.csv
Border Any substation at the end of a line or link to another country. These are always kept and do not count toward the target. cross_border
DC link Any substation at the end of a DC link. Always kept. link_bus
Coverage The country is divided into regions by k-means on substation coordinates. In each region the most important substation is kept, so no part of the country is left without a node. selected_spatial
Importance The remaining places go to the substations with the highest blended score (below). selected_importance
Industrial anchor A kept substation that is the nearest one to a cluster of industrial sites. It is protected from being merged away in the clean-up step. ccs_anchor
By hand Substations the designer adds or removes after looking at the map. manual_include

Importance of a substation is

importance = 1.0 × number of connected lines and links
           + 0.3 × voltage / 400 kV
           + 1.0 × number of cross-border connections

The blended score adds industry. Steel plants, cement plants and ethylene crackers are grouped into hubs (sites within 30 km of each other), and each hub is assigned to its nearest substation. A substation's score is 65% its share of national importance and 35% its share of industrial emissions.

The target. The designer sets a target number of domestic nodes. Of the target, 70% is filled by coverage and the rest by the blended score; industry may push the count up to 20% above the target. Border nodes come on top.

Design Border Coverage Industrial By hand
Germany kan20 (45 nodes) 27 12 6 0
India kan50 (50 nodes) 0 17 25 8

Who stays, in the two example designs

The name of a design (kan20, kan50) is a label. It is not the node count.

3. The fold

Every substation that is not kept is mapped to its nearest kept substation in the same country. bus_mapping.csv has one row per original substation with the node it folded into and the distance. Two clean-up rules follow:

  • Short lines collapse. Nodes joined by a line shorter than 30 km are merged into one. Border nodes, DC-link nodes, industrial anchors and hand-picked nodes are protected.
  • No islands. If the fold leaves a node unconnected, a line is added to the nearest node, for gaps up to 50 km.

Because nodes are real substations, a node has a real location. Its description in the model carries the nearest large city and the distance to it.

4. Corridors

After the fold, every original line runs between two nodes or inside one. Lines inside a node disappear. Lines between the same two nodes are merged into one corridor.

Corridor property How it is set
Capacity The sum of the thermal ratings of the merged lines, times 0.7. The factor covers the security margin: a network is not run at its thermal limit. It is a generic default, not a calibration to published corridor limits.
Length The longest of the merged lines
Losses 0.006% per km
Cost of new capacity 1.1 M\$ per GW per km (equal to \$1.1 per kW per km)
Design Substations → nodes Lines → corridors Files
Germany kan20 795 → 45 1,029 → 78 1_grids/output_kan20/DEU/
India kan50 348 → 50 459 → 83 1_grids/output_kan50/IND/

Result for the two example designs

Lines and links to other countries are set aside in {ISO}_cross_border_edges.csv. Germany has 34 of them, to 10 neighbours.

  • In a single-country model, imports and exports are attached at the border nodes.
  • In a multi-country model, the two countries' grids are joined: each validated cross-border link becomes a trade link between a node on one side and a node on the other, with capacity, cost and losses set as for a domestic corridor.

5. What is attached to the nodes

Existing plants

Each plant unit is assigned to its nearest node by great-circle distance ({ISO}_power_plants_assigned_to_buses.csv). See Existing Stock Characterization.

Wind and solar

Wind and solar cells are grouped into clusters inside each node's catchment, so a cluster always belongs to one node. Each cluster is connected to its node by a line whose cost and losses depend on the distance:

Connection Rule
Solar, onshore wind Cost 1.1 M\$ per GW per km; losses 0.006% per km
Offshore wind The cheaper of an AC link (298 + 4.48 per km, \$/kW) and a DC link (876 + 0.86 per km, \$/kW), scaled by region: 1.0 Europe, 0.55 China, 1.3 United States, 0.85 elsewhere

See Renewable Energy Characterization.

New thermal plants and storage

New thermal plant options are offered at every node that already hosts a coal, gas or nuclear unit above the country's size threshold for that fuel. New storage is offered at every node that hosts a unit of any fuel above its threshold.

Design Nodes open to new thermal plants Of
Germany kan20 27 45
India kan50 40 50

The rule is not fuel-specific: a node that qualifies gets every thermal option. See New Technology Characterization.

Demand

National demand is placed on nodes with two keys, one for people and one for industry. The national level, growth and hourly shape are described in Electricity Demand.

Design intent. Demand is placed on the physical network, not on administrative units. A state or province whose load is served by a substation across its border appears at that substation. Users who need results by administrative unit should treat that as a reporting layer on top of node-level results.

The population key. Cities of 10,000 people or more are taken from a world cities table. How their population reaches the nodes depends on the grid design:

Grid option File read Method
kanN (simplified designs, as in the videos) {ISO}_bus_load_share_wtddist.csv Each city's population is shared among the nodes within 100 km, in proportion to 1 / distance². Every node can carry demand.
kan, eur, cit (full networks) {ISO}_bus_load_share_dr.csv Cities are grouped into demand regions by population-weighted k-means; each region's share goes to its nearest substation. Only those substations carry demand.
syn_N (synthetic grids) {ISO}_bus_load_share.csv Shares come directly from the synthetic grid's own demand clusters.

The industry key ({ISO}_industry_load_share.csv, built by 1_grids/industry_load_key.py). Industrial electricity is split by sub-sector using the national energy balance. Sub-sectors with plant-level location data are placed at the nodes nearest their plants, weighted by capacity and electricity intensity:

Sub-sector Located by
Iron and steel Global Energy Monitor steel plants (electric-arc furnaces weigh more per tonne than blast furnaces)
Non-metallic minerals Global Energy Monitor cement plants
Chemicals and petrochemicals Global Energy Monitor chemicals inventory
Mining and quarrying Global Energy Monitor iron-ore and coal mines
All other industry The population key

A facility more than 300 km from any node is not assigned; its weight goes to the population key. In India 68% of the industry key falls back to population, because most industrial electricity is in sub-sectors with no plant-level data.

The two keys can differ sharply. In India's kan50 design the node at Jharsuguda carries 4.2% of industrial demand and 0.6% of population.

In the model. grid_modeling.py writes three things:

  1. One electricity commodity e_<node> per node, and one heat commodity h_<node>. Heat is local: there is no heat transport between nodes.
  2. A copy of each demand technology at each node that carries demand, taking e_<node> as input.
  3. A lower bound on each copy's share of national demand (FLO_MARK), set to 0.98 times the node's share. Buildings, transport and road transport use the population key; industry uses the industry key. The 2% slack keeps rounding from making the model infeasible.

Limits to know about.

  • The population key uses cities, not gridded population. Rural load is represented only through the cities near it.
  • The industry key covers four sub-sectors by location. Aluminium and other non-ferrous metals, paper and food have no global plant tracker yet and follow population.
  • Data centres are not placed by either key.

Outputs

Each design is a folder 1_grids/output_<design>/<ISO>/:

File Content
input_network/manifest.json The design's parameters: target, weights, thresholds, counts
input_network/bus_mapping.csv One row per original substation: the node it folded into, why, and how far
{ISO}_clustered_buses.csv The nodes, with coordinates, voltage and name
{ISO}_clustered_lines.csv The lines between nodes, before merging into corridors
{ISO}_cross_border_edges.csv Lines and links to other countries
{ISO}_bus_load_share_*.csv, {ISO}_industry_load_share.csv The population and industry keys
{ISO}_power_plants_assigned_to_buses.csv Plant units and their nodes
cluster_summary_*.csv, cluster_*_atlite_timeseries.csv Wind and solar clusters and their hourly profiles
{ISO}_network_visualization.html A map of the result

The model itself is written as Veda tables, not as a PyPSA network.

Resolution examples

The two figures show Germany's full network in the two source datasets. Either can be used as it is, or simplified to a chosen number of nodes with the method above.

Germany, eur dataset, full network: 795 substations, 1,029 lines { width="100%" }

Germany, eur dataset, full network: 795 substations, 1,029 lines

Germany, kan dataset, full network: 481 substations, 671 lines { width="100%" }

Germany, kan dataset, full network: 481 substations, 671 lines

Italy, kan dataset, full network: 265 substations, 365 lines { width="100%" }

Italy, kan dataset, full network: 265 substations, 365 lines

Japan, kan dataset, full network: 187 substations, 237 lines { width="100%" }

Japan, kan dataset, full network: 187 substations, 237 lines

What the grid does not do

  • No power-flow physics. Corridors carry energy up to their capacity, with losses. There are no voltage angles, reactive power or stability limits beyond the 0.7 factor.
  • Capacities are inferred. Thermal ratings come from voltage and circuit count in OpenStreetMap, not from operator data. Where an operator publishes corridor limits, those should replace the default.
  • Coverage follows the map. Where OpenStreetMap is thin, so is the network.
  • Lower voltages are absent. Distribution and sub-transmission are not modelled.

See also

Electricity Demand

National demand level, growth and hourly shape

Renewable Energy Characterization

How wind and solar clusters are built and attached to nodes

New Technology Characterization

What can be built, at what cost, and where